When it comes to starting a concrete plant, it is very important to ensure that all stages are properly prepared. In this article, we will tell you how to properly prepare for commissioning, following recommendations and standards that will help you avoid mistakes and ensure a successful launch.
[parent] => 45 [count] => 6 [filter] => raw )
Site and foundation preparation
The first thing you need to do is prepare the site and foundation for installing the equipment. This is the basis for further installation and efficient operation.
- ZZBO provides foundation load calculations that indicate the axes and dimensions of the equipment site, as well as loads in kilonewtons on support points.
Based on these data, the buyer (customer) contacts the design construction organization at the site of operation, which, taking into account geological surveys and soil characteristics, develops a foundation design. The foundation must be made strictly in accordance with the approved project, withstand all design loads and be ready for installation of equipment on time. - Area for installation of equipment: For a typical concrete plant with a capacity of up to 30 m³, the minimum area for installation of main equipment is 160 m². In addition, space should be provided for storing inert materials, silos, as well as for maintenance and repair areas.
Important! The site for the equipment must be prepared in advance so that the installation team can begin work immediately upon arrival. More details can be found in «Regulations on commissioning of ZZBO concrete plants».
Commissioning planning
Before starting commissioning work, it is important to consider the following aspects:
- Prepare the required amount of cement and inert materials that comply with GOST standards for test batches.
- Electricity and water supply must be supplied in accordance with technical requirements. It is also necessary to ensure reliable grounding and power connections.
Important technical nuances of the site
Even with a well-made foundation, it is important to provide infrastructure elements that will ensure reliable and safe operation:
- Be sure to provide stormwater and drainage with settling tanks.
- Don't forget about PTS, control panels, water and reagent tanks.
- To account for the finished product, you can set weighing control station - approximately 3x18 m with a detour.
Supervision of installation works
Installation supervision is the first stage of preparing equipment for launch, which includes:
- Assembly and installation of equipment on the foundation.
- Interfacing of assembly units, according to the configuration.
- Tying and connecting all necessary elements: dispensers, silos, conveyors.
- Installation of the necessary systems: water supply, pneumatic systems, power cables.
Commissioning works
At the next stage, commissioning work is carried out:
- Checking and setting up equipment: the technician checks the equipment for integrity, conducts tests at idle and in production mode.
- Personnel training: after checking the equipment and setting up all systems, the personnel are trained to work with the new equipment.
- Trial production: carried out to check the operation of all dispensers and mixers, as well as to test production technology.
Documentation and acts
After completion of commissioning work, a report on the work performed is drawn up, which is signed by representatives of both parties. It is important that all documents are completed correctly and in a timely manner.
Bottom line: Preparation is the foundation of success.
Preparing for commissioning requires careful preparation and attention at all stages - from foundation design to personnel training. Compliance with all recommendations and technical requirements will help avoid delays and ensure smooth operation of the concrete plant in the future.